DCPI · ISO Queue Tracker

US Interconnection Queues — Data Center Load

1,765 GW of large-load interconnection requests sit in active queues across 10 US ISOs as of Q1 2026 — 17% is tied to data centers and AI clusters. Below: per-ISO totals and top BUILD subregions (shorter queues, faster Time-to-Power).

1,765 GW
Total queued large load
307 GW
Data-center load (not classified in gen-queue feeds)
17%
DC % of queue
10
ISOs tracked
ISOTotal GWDC GWDC %Top BUILD subregions (queued GW · TTP months)
NESO604.553.7
ERCOT440.3225.0Large-load (data-center-driven) interconnection queue (?GW, ?mo) ?
MISO219.8
SPP187.6
PJM171.0
CAISO75.7
AESO25.218.6
IESO16.910.2
ISO-NE14.4
NYISO10.3

Query this live from any AI agent

Available as the get_interconnection_queue MCP tool. Add the DC Hub MCP server to Claude, Cursor, Cline, or any agent — then query queue data in any chat.

Add MCP server →

How DCPI uses queue data

Queue position and length, combined with signed-contract load growth and retiring asset capacity, feed the DCPI Excess Power score (BUILD signal in markets where the queue is quiet relative to available headroom) and Constraint score (CAUTION/AVOID where backlog drives Time-to-Power past 17-24 months). Refreshed daily from the 7 major ISOs. → Open DCPI

JSON API

GET /api/v1/interconnection-queue/snapshot # all ISOs, latest
GET /api/v1/interconnection-queue/by-iso?iso=ERCOT # single-ISO drill-down

Sources (each ISO snapshot links its primary source): ERCOT MIS · PJM Queue Tracker · MISO GIQ · SPP DISIS · CAISO · NYISO · ISO-NE · LBNL Queued Up